Tutorial 4: Action status
You might have noticed that some of your actions are colored differently from others. Actions are styled based on their status, to give you an idea of their availability.
The next action in each project is colored purple. This represents what you can do to make progress on the project.
In your sequential projects, that is, projects whose actions need to be completed in order, only the next action is considered available. The rest are colored gray to show that they are unavailable until you complete the next action.
If you change one of your projects to be parallel by clicking the twin arows to the right of the project’s name, you’ll see the actions after the next action turn black. These actions are all available, because you don’t need to do them in any particular order.